1) Confirm site basics
Look up your parcel in ZIMAS (zoning, overlays, Hillside/VHFHSZ). Check if you’re within ½-mile of major transit for the 18–20 ft height band.
2) Choose a design path
Custom plans or an LADBS Standard Plan (pre-reviewed) to speed up plan check.
3) Prepare submittals
Include site plan with setbacks (≥4 ft sides/rear for state ADUs), elevations with overall height, floor plans, Title 24 energy docs, and utility notes (sewer/water/electrical).
4) Submit via ePlanLA
Create an Angeleno account and submit your ADU for ministerial review; agencies act within statutory timelines (completeness in ~30 days; approval/denial within ~60 days of complete).
5) Permits & fees
Pay plan check/building permits; note: impact fees exempt <750 sf; school district fees may apply >500 sf. Connection fees for conversions are limited.
6) Build & inspections
Request inspections through LADBS; final Certificate of Occupancy is required before move-in.
Tip: If you’re removing a garage, you don’t have to replace off-street parking for the main house.