Modern detached ADU with cedar and dark panel cladding at dusk
HomeBlogCosts

Detached ADU Costs in 2025: What Drives Price (and How to Save)

A transparent tour of the line items—sitework, structure, utilities, finishes, design and fees—plus a live estimator you can tweak in 30 seconds.

TL;DR: Detached ADU budgets hinge on sitework + utilities, structure + labor, and finish choices. Use the estimator below to model square footage, a realistic site allowance, and a 10–15% contingency. Then lock your rules and builder shortlists to keep surprises at bay. {{verify locally for permits/fees}}

Overview
The price of a detached accessory dwelling unit is a story told in layers. First comes the lot—grading, trenching, where the sewer runs. Then the shell—foundation, framing, roof. After that, the systems—power, water, heating. Finally, the skin and soul—windows, cabinets, tile, the fixtures you’ll touch every day. In 2025, material volatility has calmed compared to peak-pandemic spikes, but labor and inspection backlogs keep pressure on schedules. That means scope clarity and sequence matter as much as raw unit costs.

Where the money goes

Category What’s inside What moves it
Sitework & Utilities Grading, trenching, sewer/water tie-in, electrical service, driveway/path, tree work Lot slope, sewer distance, soil conditions, panel capacity
Foundation & Structure Footings/slab or piers, framing, sheathing, roof framing & underlayment Soils report, frost depth, spans, roof complexity
Systems (MEP) Electrical, plumbing, HVAC/heat pump, water heater, ventilation Equipment choices, run lengths, energy code
Exterior Windows/doors, siding, exterior trim, roofing, gutters Window performance, siding type, roofing type
Interior & Finishes Drywall, paint, cabinets, countertops, appliances, flooring, tile, fixtures Spec level (builder grade vs premium), layout efficiency
Soft Costs & Fees Design, engineering, surveys, permits, impact/utility fees Local rules, scope change, number of reviews
Primary home and detached ADU connected by landscaped path
Utility runs and grading between the main house and ADU often decide early budget swings.

Detached ADU cost estimator

Use this quick planner to draft a starting budget. It multiplies square footage by an adjustable build cost, then layers in allowances for sitework, utilities, soft costs, and a contingency. Numbers are illustrative; replace with real bids as you proceed.

Base build: $262,500
Sitework + Utilities + Soft: $70,000
Subtotal (pre-contingency): $332,500
Contingency: $39,900
Estimated total: $372,400

Soft vs hard costs

Hard 70% / Soft 30%
Hard (structure, exterior, interior) Soft (site, utilities, fees)

Permit, utility, and impact fees vary widely by city and utility district—confirm on the official portal. {{verify locally}}

Warm ADU interior with kitchenette and exposed wood beams
Finish level has outsized impact on budgets. Cabinets, tile, and glazing multiply quickly.

Five ways owners saved 8–15% without regret

  1. Simplify the roof. Fewer hips/valleys cut framing and roofing labor. Subtle fascia details can keep the look sharp.
  2. Right-size windows. Put glass where it matters (living, kitchen sink, bed) and skip picture windows on low-value walls.
  3. Keep wet walls stacked. Align kitchen/bath to shorten plumbing runs and venting. It’s not glamorous, but it’s gold.
  4. Spec durable, not delicate. Choose floors/tile that are attractive and repairable. Rental-friendly finishes keep lifecycle costs low.
  5. Coordinate inspections. Batch work to reduce re-mobilization. Clear sequences shave weeks off schedules.

These moves preserve function and comfort. Deep cuts—like shrinking insulation or airflow— tend to boomerang as long-term costs. Keep performance intact; trim complexity first.

Framed walls of a detached ADU under construction
Case A — 750 sf detached with simple gable roof.

Case A: 750 sf detached (simple gable)

Scope: Slab-on-grade, heat pump, mid-grade windows, fiber-cement siding, modest deck.

Line itemBudget (example)
Base build$262,500
Sitework & utilities$46,000
Soft costs & fees$22,000
Contingency (10%)$33,450
Total (illustrative)$363,950

Example only. Replace with local bids and fee schedules. {{verify locally}}

Garage conversion ADU with upgraded exterior
Case B — 420 sf garage conversion (for cost contrast).

Case B: 420 sf garage conversion (contrast)

Scope: Keep existing slab and walls where feasible; insulate, new windows/door, bath + kitchenette.

Line itemBudget (example)
Base build$126,000
Sitework & utilities$18,000
Soft costs & fees$12,000
Contingency (12%)$18,480
Total (illustrative)$174,480

Conversions differ by existing conditions; seismic and water-proofing can add scope. {{verify locally}}

Walkthrough: from permit set to punch list. Batching inspections reduces idle time and change orders.

Timeline & cash flow

Detached ADUs typically pass through six phases: feasibility → design → permits → sitework → shell → interior. Your cash flow follows. Early invoices are soft costs and deposits; the heavy lifts land during foundation, framing, and rough-in. If you’re using a loan with draws, align your contractor’s schedule to the lender’s inspection cadence to avoid delays. Interest-only periods can ease the middle months while you order long-lead items and finish interiors.

Owners renting the ADU often model two calendar years: Year 1 covers design, permits, and build (with interest-only payments). Year 2 starts rent-up and stabilization. A small reserve—two months of payment and a buffer for utility trench surprises—keeps the project calm when reality deviates from plan.

FAQ

Is prefab cheaper than site-built?
Sometimes. Factory efficiency can lower labor and shorten schedules, but sitework, foundation, craning, utility hookups, and finishes still apply. Compare delivered-and-set price + site costs against a site-built bid on the same scope.
What square footage hits the best cost-per-foot?
Very small ADUs (under ~350 sf) have high per-foot costs due to kitchen/bath fixed costs. Units in the 500–800 sf band often balance efficiency with livability. Above that, envelope and finish areas grow faster than functions.
How much contingency should I carry?
10–15% is common for well-scoped projects; go higher with unknown utilities, complex grading, or design-in-progress.
What fees blindside owners?
Utility connection fees, school/transport impact fees (where applicable), and plan review resubmittals. Check your city and utility portals for current schedules. {{verify locally}}
Where should I spend more, not less?
Thermal envelope, air sealing, ventilation, and windows you’ll open daily. Those improve comfort, durability, and long-term operating costs.
What’s the best next step after budgeting?
Confirm what you can build on your lot via the regulations hub, then send a concise RFQ to 2–3 builders using our /estimate form.

Next steps